F-22 program on track
Released: 22 Dec 1999
courtesy USAF photo
WASHINGTON (AFPN) -- An Air Force program official
expressed continued confidence that the F-22 program will meet
projected delivery schedules and cost limitations.
Speaking recently before the House subcommittee
on national security, veterans affairs and international
relations, Darleen Druyun, principal deputy assistant for Air
Force acquisition and management, said, "I believe that we will
be able to meet the schedule we have clearly laid out here."
Also speaking before the committee was Dr. George Schneiter,
Department of Defense director of strategic and tactical systems,
who spoke about the DOD's efforts to control costs and adhere to
the F-22 schedule.
Adjusted cost limits for the F-22 program are $18.9 billion for
engineering and manufacturing development and $39.759 billion for
production. The caps were mandated by the National Defense
Authorization Act for fiscal 1998.
Druyun countered written testimony by the Government Accounting
Office that the Air Force is not doing enough to limit costs.
She cited several milestones the program has achieved to date and
the initiatives under way to offset a projected "worst-case"
analysis of $660 million in engineering and manufacturing
development costs above the cost cap, cited by a March 1999 GAO
report.
"Back in March 1999, I reported we had offsets, dollar for
dollar, for the potential cost growth. Today ... we have
identified an additional $200 million for a total of $860 million
... of offsets to handle this worst case shortfall that we
predicted back in March of '99," Druyun said.
"The EMD cost savings demonstrate the creative things the program
can do to reduce costs," according to Druyun's written statement.
As for production cost limits, Druyun said cost reduction
initiatives through July total $16.9 billion -- an increase from
earlier estimates of nearly $10 billion in cost reductions.
One challenge is the avionics package. She said projected
delivery of the avionics software delivery blocks is on track.
"We are pleased to report on the tremendous progress we are
making in this arena," she said, adding software delivery is
either on schedule or ahead of schedule.
In fact, she said, the avionics delivered to date represent 50
percent of the software that needs to be delivered "... and each
... has been delivered as we had predicted or actually a little
bit ahead of schedule."
Druyun also commented on the successful testing phase under way.
The F-22 has undergone more than 45,000 hours of wind tunnel
testing; over 60,000 hours of subsystem laboratory testing, over
10,000 hours of radar testing and 14 live fire tests on aircraft
components.
"Today, our flight test hours on our two development aircraft are
around 480 hours," she said. "And by December of 2000, we
project that we will have over 1,000 flight test hours underneath
our belt."
"I would also point out that almost 29 percent of our test points
have been completed for the flying qualities of this aircraft.
"This is a very tough program to manage," Druyun said. "I think
I have the best team within the Air Force and within the
contractor community aggressively working this program. Our
avionics is very much on track and all blocks are meeting or
exceeding the JET's (Joint Estimate Team) delivery dates.
"... I would like to reiterate that F-22 development and
production costs are very carefully managed, and I can continue
to report ... that they are within the congressional cost caps,"
Druyun concluded.
|